Bid Opening for Construction of Second Carriageway and Reconstruction of the Existing One on the Main Road M4, Road Section Tuzla (Dreznik) - Sicki Brod
Sarajevo, November 29, 2011 – Bid Opening for Construction of Second Carriageway and Reconstruction of the Existing one on the Main Road M4, Road Section Tuzla (Dreznik) - Sicki Brod was organized yesterday in the business premises of the PC Roads of the Federation of BH.
Seven companies have submitted their Bids by the Deadline for Bid Submission:
- JV ROADING d.o.o. Gracanica, ARAPOVAC PUTEVI d.o.o.Celic, EKO PROM d.o.o. Brcko and CONRAM d.o.o. Brcko,
- PRIJEDORPUTEVI a.d. Prijedor
- JV JATA GROUP d.o.o. Srebrenik, EUROASFALT d.o.o. Sarajevo, GP PUT d.d. Sarajevo and DELING d.o.o. Tuzla
- HP INVESTING d.o.o. Mostar
- JV RIAL SPED d.o.o. Doboj East, REWEUS d.o.o. Lukavac, KLAUS LEHMANN GmbH
- INTEGRAL INZINJERING a.d. Laktasi
- STRABAG A.G. Austria
Bidding Procedure for Construction of Second Carriageway and Reconstruction of the Existing One on the Main Road M4, Tuzla (Dreznik) – Siscki Brod was launched on October, 17, 2011 and closed on November 28, 2011. Bidding Procedure was launched in accordance with the criteria set by the Law on Public Procurements of BH. According to the criteria, works will be awarded to the lowest evaluated Bidder complying with all requirements – technical, financial, qualification references etc.
It was immediately preceded with Bid Evaluation of the results of which, including the selection of new Bidder, the public will be notified accordingly.
Deadline for Works Completion is 10 months from the Access to Site Date.
|